Cahokia Heights FAQs

The U.S. Army Corps of Engineers, St. Louis District is supporting the community of Cahokia Heights, Illinois, with project and technical assistance under various locations in the community.  

Wastewater Infrastructure FAQs

Expand List item 30380Collapse List item 30380  What is the Section 219 Environmental Infrastructure Program? 

The Environmental Infrastructure Program is a Congressionally enacted authority under Section 219 of the Water Resources Development Act (WRDA) of 1992. The Section 219 authority provides the U.S. Army Corps of Engineers (USACE) the ability to assist non-Federal interests, such as a city or county government, in carrying out water-related environmental infrastructure and resource protection and development projects. Assistance may be in the form of design, construction, or design and construction for wastewater treatment and related facilities and water supply, storage, treatment, distribution facilities and stormwater management. 

Expand List item 30382Collapse List item 30382  What, in the coordination with local government, the City Engineer, and USEPA, is the process for deciding which feature of work to pursue under this program?

In March 2022, the city Engineer informed USACE that the best opportunity would be to assist with cured-in-place-pipe (CIPP) lining of a large portion of sanitary sewer trunkline. USACE coordinated the proposed project with USEPA Region 5 officials who validated it was a necessary project. USACE initiated a federal decision document called a Letter Report in May 2022 to document our federal assistance project. Our planned support is focused on the trunkline that runs nearly the length of the city from northeast to southwest, picking up all sanitary sewer lines along the way, before reaching the southernmost pump station on Levin Drive. If the trunk sewer line fails, then the entire sanitary sewer collection and transport network fails for the entire city. Therefore, this assistance project is a critical part of the sanitary sewer infrastructure as it serves as the main conduit that carries all water from a flushed toilet, sink or bathtub drain to the American Bottoms Wastewater Treatment Plant for processing.

Expand List item 30383Collapse List item 30383  What is “cured-in-place” pipe, how does it avoid an open excavation repair and why is it the optimal means of addressing the section of pipe we’re looking to do the work on?

Trenchless methods of rehabilitation use the existing pipe as a host for a new pipe or liner. Trenchless sewer rehabilitation techniques offer a method of correcting pipe deficiencies without execution of a labor-intensive dig and-replace method. A trenchless sewer rehabilitation method known as Cured-in-place pipe (CIPP) renewal process will be used and involves a flexible fabric liner, coated with a thermosetting resin, inserted into the existing pipeline and cured to form a new liner. The liner is typically inserted into the existing pipe through an existing manhole. The fabric tube holds the resin in place until the tube is inserted in the pipe and ready to be cured. Commonly manufactured resins include unsaturated polyester, vinyl ester, and epoxy, with each having distinct chemical resistance to domestic wastewater. The CIPP method can be applied to rehabilitate existing sewer lines with defects such as cracks, offset joints, and structurally deficient segments. The thermosetting resin material bonds with the existing pipe materials to form a tighter seal than most other trenchless techniques. The two primary methods of installing CIPP are winch-in-place and invert-in-place. The more typically applied inversion-in-place method uses gravity and either water or air pressure to force the tube through the pipe and invert it or turn the tube inside out. This process of inversion presses the resin-coated tube against the walls of the existing pipe. During both methods, heat is then circulated through the tube to cure the resin to form a strong bond between the tube and the existing pipe.

Expand List item 30384Collapse List item 30384  Explain the decision behind the location of our proposed work? Why does it matter to the communities it will serve? 

Following the request by the city in March 2022, USACE conducted a site visit with USEPA as well as coordinated the request through our interagency partnership meeting with Federal and State agencies for review and concurrence. This trunkline runs nearly the length of the city from northeast to southwest, collecting and transporting all the sanitary sewer lines along its path, before reaching the southernmost pump station on Levin Drive. If the trunk sewer line fails, then the entire sanitary sewer collection and transport network fails for the entire city. Therefore, this assistance project is a critical part of the sanitary sewer infrastructure as it serves as the main conduit that carries all water from a flushed toilet, sink or bathtub drain in the city and is transported to the American Bottoms Wastewater Treatment Plant for processing. The city and their engineer through various grant sources have secured funding to address sanitary sewer components that enable transport to the sanitary sewer trunk line. These components include the repair, rehabilitation, and replacement of gravity sewer mains, force mains and sewer laterals and lift station upgrades. Collectively these improvements are intended to eliminate sanitary sewer overflows, reduce or eliminate system surcharging, eliminate sewer service backups, reduce operation and maintenance cost, meet level of service expected by the community and increase reliability and continuity of sewer service.    

Expand List item 30385Collapse List item 30385  Explain tributary lines and where they go (which communities they lead to, by street). 

For details on how your sanitary sewer is oriented in your neighborhood, please contact your city officials. 

Expand List item 30387Collapse List item 30387  Explain the cost-share relationship between the USACE Federal dollars and the non-Federal sponsor’s financial responsibility? 

The Federal share of the project cost is 75 percent, and the city must contribute at least 25 percent of the total project costs. USACE will advertise and award a competitive contract after execution of the Project Partnership Agreement. USACE will perform quality assurance, manage all contract administration actions, and coordinate construction inspection activities during construction. After construction is complete, the city is responsible for future Operation, Maintenance, Repair, Rehabilitation and Replacement. 

Expand List item 30388Collapse List item 30388  Explain the implementation responsibilities and BCOES review process and how the USACE completes the contract administration and QA/QC’ing of the project. 

The City of Cahokia Heights, through their contractor Hurst-Rosche, Inc., will finalize plans and specifications for the proposed project and submit them to USACE. Plans and specifications for work to be performed will be formatted into USACE standards and a Biddability, Constructability, Operability, Environmental and Sustainability (BCOES) review will be conducted by a team of technical experts. After completion of the BCOES review, USACE will move forward with advertisement and award of a competitive contract. USACE will perform quality assurance, manage all contract administration actions, and coordinate construction inspection activities during construction of the project. Once the project is completed it is turned over to the non-Federal sponsor who is responsible for 100% of the operations and maintenance on the project.

Flood Hazard Analysis FAQs

Expand List item 30373Collapse List item 30373  What is a 100-year flood?

Flood hazard areas identified on the FEMA Flood Insurance Rate Map are identified as a Special Flood Hazard Area (SFHA). SFHA are defined as the area that will be inundated by the flood event having a 1-percent chance of being equaled or exceeded in any given year. The 1-percent annual chance flood is also referred to as the base flood or 100-year flood. While the community is protected from overbank Mississippi River flooding the area is still vulnerable to flooding based on flat low-lying terrain, impervious surfaces such as asphalt and concrete, soils with slow infiltration and overall poor drainage following heavy rainfall.

Expand List item 30374Collapse List item 30374  How does the metro east levee system reduce flood risk?

The East St. Louis Levee System is located in Madison and St. Clair Counties, Illinois. The Federal project, originally constructed between the 1930s and 1950s, reduces the risk of flooding from the Mississippi River to the communities of East St. Louis, Cahokia Heights, Sauget, Madison, Brooklyn, Venice, Fairmont City, and Granite City and many heavy and light industries, airports, transportation hubs, and hospitals. The levee system has undergone several major modifications, including most recently projects to correct underseepage deficiencies. The system is nearly 29 miles in length and consists of two segments: the Metro East Sanitary District (MESD) levee, operated by local interests, and the Chain of Rocks East levee, operated by USACE.  The East St. Louis levee system has prevented the communities from Mississippi River flooding during numerous major flood events and has been recently accredited by FEMA.

Expand List item 30378Collapse List item 30378  What proposals have state and federal agencies identified in the past to address the flooding issues? Which of these proposals have been completed? Which have not?

This is not intended to be a comprehensive list as there are many prior efforts that USACE is unaware of.

  • East St. Louis & Vicinity Ecosystem Restoration Study (USACE) - Complete
  • Canal 1 Reach B Emergency Work and Maintenance (MESD) - Complete
  • Prairie Du Pont Watershed Study (Heartlands Conservancy) –  Complete
  • Cahokia Heights and East St. Louis Flood Hazard Analysis (USACE) – Complete
  • Piat Place and Harding Ditch Report (USACE) – Complete
Expand List item 30379Collapse List item 30379  What is USACE authorized to do under the authority being used for the Flood Hazard Analysis study? Will USACE be implementing any of the recommendations from the study?

The Floodplain Management Services (FPMS) program (authorized by Section 206 of the 1960 Flood Control Act) provides information on flood hazards to local interests, State agencies, Tribes, and other Federal agencies to guide floodplain development. FPMS program services are provided to State, Tribal, regional, and local governments at no cost, within program funding limits.  The documents are intended to provide the local communities with alternatives that are feasible.             

Contact Information

U.S. Army Corps of Engineers
St. Louis District
Programs & Project Management

1222 Spruce Street
St. Louis, MO 63103-2833
(314) 331-8012