Formerly Utilized Sites Remedial Action Program (FUSRAP)

AUTHORIZATION:  Energy and Water Development Appropriations Act of 1998 provided authorization for the Corps of Engineers to execute this program.

FUSRAP map
Project Map

HISS
Latty Ave property excavation (HISS)

SLDS
Remedial action at City Property (SLDS)

SLAPS
Backfill after remediation (SLAPS VP)

Location and Description:  There are currently five sites within the St. Louis District FUSRAP. The St. Louis Airport Site (SLAPS) consists of 21.7 acres north of Lambert International Airport in North St. Louis County, Missouri. The site is bordered by McDonnell Boulevard on the north and east, Coldwater Creek on the west, Banshee Road and Norfolk and Western Railway on the south. The SLAPS Vicinity Properties (SLAPS VPs) site consists of 78 properties in North St. Louis County, Missouri. The contaminated properties include former ball fields (located directly north of SLAPS), areas along haul roads, and Coldwater Creek. The Latty Avenue Properties site is comprised of several different tracts of land in North St. Louis County, Missouri. It includes an 11-acre site, encompassing the Hazelwood Interim Storage Site and FUTURA Coatings Company property on Latty Avenue, and the nearby Latty Avenue Vicinity Properties. The St. Louis Downtown Site (SLDS) and vicinity properties are located on and around the Mallinckrodt facility in St. Louis, Missouri. There are 17 acres where contaminated soils are accessible for remediation without major disruption of plant operations. The Iowa Army Ammunition Plant (IAAAP) site consists of approximately 1,600 acres of land within the approximately 19,000-acre plant in Middletown, Iowa. The exact scope of the Iowa project is not known at this time as a Remedial Investigation/Feasibility Study is underway.

Activities in FY 2010 ($48,200k)
- Latty Ave: Continue remediation, remove/ship 17,000 cy; issue final post remediation documents for 2 Vicinity Properties (VPs)
- St Louis Downtown Site: Continue remediation; remove 10,000 cy from Plant 6 West area, BNSF railroad, and City Property vicinity area; release five properties; complete sampling and initiate Remedial Investigation and Feasibility Report for the Inaccessible Areas Operable Unit
- St. Louis Airport Site Vicinity Properties: Continue remediation; remove 8,000 cy; and prepare post-remedial documentation for 6 VPs.
- St. Louis Airport Site: Perform post-remediation monitoring and long-term management activities

ARRA Allocation thru 28 Feb 10 ($2,000k)
-
Remediate five additional SLAPS vicinity properties

President’s Budget for FY 2011 ($40,700k)
- Latty Ave Sites:
Remove 12,000 cy and issue release documents for two additional VPs
- St. Louis Airport Site Vicinity Properties: remove/ship 7,000 cy; issue post remediation documents for 8 VPs
- St. Louis Downtown Site: Remove/ship 9,000 cy from vicinity properties and finalize Remedial Investigation and Feasibility Reports for the Inaccessible Areas Operable Unit
- St. Louis Airport Site: Perform post-remediation monitoring and long-term management activities