The St. Louis Corps Of Engineers Permits Office Closed Public
Notices 2005
- P-2498.pdf -
Application by Mr. Paul McKee Jr., to conduct grading and filling
operations in waters of the United States, on a 12-acre site, in
conjunction with the development of a school and associated grounds
known as Barat Academy. The total proposed impacts to
jurisdictional waters are 340 lineal feet of stream channel and 0.33
acres of wetlands. The project area is located east of and
adjacent to Highway 40/61, approximately 2 miles northwest of the
intersection of Missouri Highway K and U.S. Highway 40, in Dardenne
Prairie, St. Charles County, Missouri. The Public Notice comment
period opens on November 4, 2005, and closes on November 25, 2005
- P-2504 Pointe Prairie, L.L.C. has submitted a Mitigation Bank Prospectus to
restore, enhance, and preserve a 4,750 foot long section of Little
Dardenne Creek and associated riparian corridor for purposes of
offering an additional source of compensation for impacts to
tributaries within the proposed geographic service area. Little
Dardenne Creek is a tributary to the Mississippi River and is located
within St. Charles County, Missouri.
-
P-2505.pdf - The applicant, Mr. Stephen
Hoffmeyer, requests permission to permanently moor a 26-foot by 67-foot
barge converted into a private residential vessel upstream of Portage
des Sioux, Missouri. (The project was previously presented under
public notice P-2426 and subsequently authorized. Since the
public notice in July of 2004, a "stick-built" home, approximately 1920
square feet in size, has been retrofitted on the barge to establish a
private residential structure.) The project
is located on the right descending bank of Mississippi River mile
113.4, St. Charles County, Missouri. Specifically, the project is
located on the Elsah USGS quadrangle map, latitude 38:56:13.0921,
longitude -90:21:26.6721.
-
P-2508.pdf
- The St. Louis District Regulatory Branch,
requests approval under the Clean Water Act to reissue
Regional General Permit 16 for bank stabilization activities within the
State of Illinois. The
associated 21-day public notice comment period,
while stated as being open from
November 18, 2005
through
December 9, 2005,
will actually be open till December 16, 2005
- P-2485.PDF
Application by Mr. Dwight Billingsley, to conduct grading and filling
operations in waters of the United States in conjunction with the
development of an 8.2-acre site for a senior living community. The
total proposed impacts to jurisdictional waters are 80-lineal feet of
stream channel and 0.66 acres of wetlands. The project area is located
between McKelvey Road and Interstate 270, in Maryland Heights,
Missouri. The project area is adjacent to Fee Fee Creek, which is a
secondary tributary to the Missouri River. Open`s September 13, 2005,
Closes October 3, 2005.
- P-2484.PDF
Mr. Don Glosier, Glosier Realty Advisors, L.L.C. requests authorization
under Section 404 of the Clean Water Act to develop a 74-acre site into
a commercial and retail business center. The site is located west of
Highway 61, and to the north and south of Wentzville Parkway in
Wentzville, St. Charles County, Missouri. The Public Notice opens
August 3, 2005 and closes on August 24, 2005.
- P-2483.PDF
The Lake St. Louis Community Association requests authorization to
dredge approximately 8,000 cubic yards of accumulated sediments from
Lake St. Louise, in St. Charles County, Missouri. The comment period
opens on July 20, 2005 and expires on August 9, 2005.
- CEMVS_MGP_4.PDF
A joint Public Notice with the Kansas City District for renewal of the
Missouri General Permit for the construction, installation, and
maintenance of fixed or floating private boat docks, no larger than
40-feet-long by 20-feet-wide, with attendant features that are
necessary for the use and maintenance of the dock, i.e. walkways,
piers, deadmen, and stairs. In addition, minor discharges up to 25
cubic yards, including the volume of any area excavated, which are
necessary for installation of the dock and protection of the adjacent
riverbank. No commercial docks are authorized. These docks will be
located along the Missouri River, Mississippi River, and navigable
portions of the Meramec River and Salt River. The Public Notice opens
July 15,
2005 and closes on August 15, 2005.
- P-2478.PDF
Mr. Brian Pendleton, Golden Management, Incorporated, requests
authorization under Section 404 of the Clean Water Act to develop a
33-acre site into a residential community. The site is located north of
Illinois Route 156 and south of Turtle Dove Road immediately west of
Waterloo, Monroe County, Illinois. The Public Notice opens June 27,
2005 and closes on July 18, 2005.
- P-2477.PDF
Mr. John Holthaus, Gateway Development, requests authorization under
Section 404 of the Clean Water Act to develop a 33.5-acre site into a
residential community to be called Stone Bridge Villas. The project is
located 1/4 mile north of Frank Scott Parkway and immediately east of
Hartman Lane in O'Fallon, St. Clair County, Illinois. The public notice
opens June 28, 2005 and closes on July 19, 2005.
- P-2476.PDF
Mr. Ernest Dennison, P.E., Waste Management of Illinois, Incorporated,
requests authorization under Section 404 of the Clean Water Act to
develop a 222-acre parcel of vacant land to be called North Milam. The
project site is located west of Canteen Lake and north of the existing
Milam Recycling and Disposal Facility near Madison, Madison County,
Illinois. The Public Notice opens June 30, 2005 and closes July 21,
2005.
- P-2482.PDF
The U.S. Army Corps of Engineers, Project Management Branch requests
authorization to install rip rap along 1,607 linear feet of the river
bank adjacent to the existing Cape Girardeau Flood Protection system.
The activity is located along the left descending bank of the
Mississippi River, between approximate river miles 51.6 and 52.8, in
Cape Girardeau, Cape Girardeau County, Missouri. The public notice
opens on June 29, 2005 and closes on July 19, 2005.
- P-2481.PDF
The Metropolitan St. Louis Sewer District requests authorization to
reconfigure 1,280 linear feet of existing Black Jack Creek channel into
a U-shaped concrete lined channel for a project known as Hallstead
Storm Channel Phase IV. An additional 120 linear feet of creek channel
would be rock lined to create a plunge pool to dissipate water
velocities before the concrete channel would transition back into the
natural creek channel. The project purpose is to eliminate creek bank
erosion and improve conveyance to reduce potential for overbank
flooding within the project limits. Black Jack Creek flows into Maline
Creek, which is a primary tributary to the Mississippi River. The
Public Notice opens June 27, 2005 and closes on July 18, 2005.
- P-2480.PDF
American Riverway Property LLC :A proposal to permanently moor a
stationary three story floating banquet vessel, a deflection barge and
three associated boarding ramps are requested at Mississippi River Mile
202.9, in Alton, Madison County, Illinois. The Public
Notice opens June 22, 2005 and closes on July 12, 2005.
- P-2475.PDF
The Madison Warehouse Corporation requests permit authority to fill
0.25 acre of wooded wetlands for expansion purposes. The Public
Notice opens May 23, 2005 and closes on June 13, 2005.
- P-2474.PDF
City of Dardenne Prairie requests authorization to channelize
approximately 900 linear feet of unnamed tributary by constructing 645
linear feet of new trapezoidal channel to alleviate flooding on two
residences in the Dardenne Landing subdivision. The tributary flows
into Lake St. Louis, which is an impoundment of Peruque Creek. Peruque
Creek is a primary tributary to the Mississippi River. The Public
Notice opens May 6, 2005 and closes on May 27, 2005.
- P-2470.PDF
Triad Development requests authorization to site grade in connection
with an 8-acre commercial development, known as the Highway W Tract,
which will impact approximately 883 linear feet of an unnamed tributary
to Big Creek in North St. Charles County, Missouri. Big Creek flows
into the Cuivre River that is a tributary to the Mississippi River. The
Public Notice opens on April 29, 2005 and closes on May 20, 2005.
- P-2473.PDF
The applicant, New Bourbon Regional Port Authority, requests
reauthorization to construct a slackwater harbor and public transfer
facility. The original authorization, Department of the Army permit #P-1833.PDF,
was issued in April of 1995. This current public notice covers all
aspects of the original permit initially applied for, as well as parts
of the project that have been completed. The project is located on the
right descending bank of Mississippi River mile 120.5, Ste. Genevieve
County, Missouri. Specifically, the project is located on the Kaskaskia
USGS quadrangle map, US Survey 67, Township 38 North, Range 09 East.
The Public Notice opens May 02, 2005 and expires on May 16, 2005.
- P-2472.PDF
Calvary Church requests authorization to site grade in connection with
the construction of the Calvary Church - West Camps. Grading for the
site will impact approximately 0.49-acres of emergent wetland adjacent
to Big Creek in North St. Charles County, Missouri. Big Creek flows
into the Cuivre River that is a tributary to the Mississippi River. The
Public Notice opens on April 25, 2005 and closes on May 16, 2005.
- P-2471.PDF
Hecht Construction Company seeks authorization to fill approximately
1035 lineal feet of two, intermittent, unnamed tributaries to
facilitate residential lot development, including associated roadways
and utility infrastructures. The purpose of the project is to provide
single-family housing and associated structures to serve the proposed
residential community, known as San Luis Trails. The project is located
near Murphy, Jefferson County, Missouri.
River. The Public Notice opens on April 27, 2005 and closes on May 18,
2005.
- P-2469.PDF
City of Wentzville requests authorization to construct a stormwater
detention overbank area that will include 800 linear feet of channel
modifications to an unnamed tributary of Dry Branch, which flows to
McCoy Creek in Wentzville, St. Charles County, Missouri. McCoy Creek
flows into the Cuivre River that is a tributary to the Mississippi
River. The Public Notice opens on April 18, 2005 and closes on May 10,
2005. Due to technical difficulties the comment period will be extended
until May 12, 2005.
- P-2468.PDF
THF Highway DD Development, L.L.C. requests authorization to site grade
in connection with the development of a 200-acre retail development on
a 264-acre parcel along US 40/61 in O'Fallon, St. Charles County,
Missouri. The proposed project will impact approximately 8,459 linear
feet of 3 different unnamed tributaries to O'Day Creek, which flows to
Dardenne Creek, a tributary to the Mississippi River. The Public Notice
opens on April 8, 2005 and closes on April 29, 2005.
- P-2466.PDF
The applicant, Triad Development, Inc. has submitted an application for
a Department of the Army Permit to develop 166 single-family homes,
roadways, and infrastructure on a site located in Lincoln County,
Missouri. The proposed development is known as Anna Meadows. The
project, if approved, will impact approximately 1,435 linear feet of
unnamed tributaries, a 1.46-acre pond, and a 0.61-acre wetland. The
Public Notice opened April 1, 2005 and expires on April 22, 2005..
- P-2463.PDF
Holcim (US) Inc. requests authorization to conduct grading in
conjunction with the expansion of an existing quarry operation at
their plant near Clarksville, Pike County, Missouri. The proposed
project will impact approximately 7000 linear feet of an unnamed
tributary to Calumet Creek, which flows into the Mississippi River.
The Public Notice opens April 7, 2005 and expires on April 28,
2005.
- p-2467.PDF
Eagle Marine Industries, Inc., requests authorization to relocate
their anchor fleet downstream of the existing fleeting location, at
Mississippi River Mile 175.6, in East St. Louis, St. Clair County,
Illinois. The Public Notice opens March 22, 2005 and expires on
April 12, 2005.
- p-2447,
p-2448, p-2449, p-2450, p-2451, p-2452, p-2453, p-2454,
p-2455.PDF Tower Rock Stone Company seeks authorization
to expand fleeting, conduct maintenance dredging and terminal
maintenance activities between Missississippi River Mile 126.1 to
127.2 in Ste. Genevieve County, Missouri. The Public Notice opens
March 18, 2005 and expires on April 7, 2005.
- p-2459
p-2460
p-2461.PDF Luhr Bros., Inc. requests authorization to
expand fleeting and conduct periodic maintenance dredging within
their existing terminal facility between Mississippi River Miles
127.4 to 127.8 in Ste. Genevieve County, Missouri. The Public
Notice opens March 18, 2005 and expires on April 7, 2005.
- p-2464.PDF
The applicant, Medical Office Development Advisors, Inc. has
submitted an application to develop a new medical office building
and associated parking area on Des Peres Hospital property in Des
Peres, St. Louis County, Missouri. The project, if approved, will
cover approximately 515 linear feet of an unnamed tributary with a
concrete pre-cast bridge structure. An approximate 0.13-acre
emergent wetland will also be filled to facilitate development. The
reach of unnamed tributary proposed for impact is a mitigation area
that has been deed restricted to fulfill conditions of a Missouri
Department of Natural Resources 401 Water Quality Certification
dated October 12, 1999. The Public Notice opens March 11, 2005 and
expires on April 1, 2005.
- p-2465.PDF
The applicant, Burkemper Land Development, Inc., proposes to fill
approximately 3.59 acres of jurisdicational waters of the U.S. for
the development of a single-family residential subdivision known as
Stonegate. The proposed activity is located near Wentzville, St.
Charles County, Missouri. Opens March 11, 2005 and Closes April 1,
2005.
- p-2462.PDF
. The Public Notice opens February 22, 2005 and expires on March
15, 2005.
- p-2429a.PDF
Maintenance Dredging proposed by Ameren Energy Generating Company
with the dredging of two areas, both approximately 750 feet, 60
feet wide and and 10 feet deep, from in front of the intake and
discharge areas of the Grand Tower Power Plant. The proposed
disposal area is the existing approved Corps of Engineers dredge
disposal site located just downstream of the dredge area, along the
left descending bank. The project is located approximately at
Mississippi River Mile 89.1, near Grand Tower, Jackson County,
Illinois. Opens February 17, 2005 and Closes March 4, 2005.
- p-2458.PDF
Paul Koch application to construct an approximate 50-foot high, 600
foot long earthen dam for purpose of creating a 28-acre
recreational lake on his property. Approximately 280 linear feet of
an unnamed tributary will be filled for construction of the dam and
an additional 4,400 linear feet of jurisdictional tributary
channels would be inundated with water. Project is located
southeast of Morse Mill, Missouri. The Public Notice opens January
28, 2005 and expires on February 18, 2005.
- p-2457.PDF
The applicant, Mr Alan Bornstein, THF Greenmount Development, LLC,
has applied for a permit to develop a 140 acre site for a joint
commercial and residential project located just north of Illinois
Route 161 (Carlyle Avenue) and east of Greenmount Road in
Belleville, St. Clair County, Illinois. The Public Notice opens
January 28, 2005 and expires on February 18, 2005.
- P-2396
St Peters levee.PDF Transcripts
from Public Hearing held on
October 21, 2004, for P-2396; application by the City of St.
Peters, Missouri, to construct a new levee, in the Mississippi
River floodplain, in St. Peters, Missouri. The proposed levee would
provide flood protection to a proposed multi-use development area
known as Lakeside Business Park. The levee would provide protection
from a 500-year flood, to a 1400 acre area. See public notice for
details. The original public notice for the application is
available at: P-2396a
- p-2439.PDF
Ms. Sharon N. Helms, 7126 Goshen Road, Edwardsville, IL 62025 has
applied for a Section 404 permit for the relocation and improvement
of 700 feet of the south unnamed tributary to Dunlap Lake in order
to accommodate existing and future land development along Goshen
Road on the southeast edge of Edwardsville, Madison County,
Illinois.The Public Notice opens January 25, 2005, and expires
February 15, 2005.
- p-2456.PDF
An application was made by Vantage Development Company, to
construct a residential subdivision to be known as Fountain Place.
The subdivision is located west of Old Collinsville Road and south
of Milburn School Road in St. Clair County, Illinois. The project,
if approved, will impact approximately 4.42 acres of linear
wetlands. The wetlands are within an unnamed secondary tributary to
the Mississippi River. The Public Notice opens January 19, 2005,
and expires February 9, 2005.
- p-2435.PDF
City of Greenville stabilize the shore of Governor Bond Lake Bond
County, Illinois. . The Public Notice opens January 13, 2005, and
expires February 4, 2005.
- p-2416.PDF
public notice describing a proposal by the Mississippi River 4
wd-ATV O.H.V.N.F.P., For After the Fact authorization to develop an
off road, 4 wheel drive recreational facility with designated
trails, mud drag racing course, mud pit, mud alley and other
support structures. This authorization should include authorization
for impacts already incurred as the result of dredging and filling
activities to construct portions of the trails, the pond, mud
alley, mud pit and the mud drag strip. The project area is located
in Section 19, Township 5 North, Range 9 West, in Wood River,
Madison County, Illinois. The Public Notice opens January 13, 2005,
and expires February 12, 2005.
- p-2445.PDF
The applicant requests authorization to conduct periodic
maintenance dredging and to construct a steel faced dock along the
right descending bank of the Illinois River, approximate mile
65.The Public Notice opens December 28, 2004, and expires January
17, 2005.
- p-2446.PDF
Attached for your comment and review is a public notice describing
a proposal by the Lange- Steggman Company to conduct maintenance
dredging and open river dredge disposal operations at their
existing river terminal along the right descending bank of the
Mississippi River at approximate river mile 182.7, in St. Louis
County, Missouri.The Public Notice opens December 17, 2004, and
expires January 3, 2005.
Last Edited:
12/12/2007 09:51 AM
|